Ongoing Progress Report (OPR) Instructions



Detailed instructions on how to complete the OPR are below. Use these instructions when reporting on the status of your activities, when responding to the request for information contained in the OPR.


Item 1: Enter legal name of the grantee.


Item 2: Enter the grant number assigned by the U.S. Department of Health and Human Services, the Administration for Children and Families, the Administration for Native Americans (ANA). This number is found in Item 3 on the Notice of Award (NOA).


Item 3a: Enter the grantee DUNS number (received from Dun and Bradstreet). This number is found in Item 25 on the NOA.


Item 3b: Enter the Employer Identification Number (EIN) assigned by the Internal Revenue Service. This number is found in Item 22 on the NOA.


Item 4: Enter grantee name and complete mailing address, including zip code.


Item 5: Select “Yes” if the SF-425 was submitted to the Payment Management System (https://pms.psc.gov/). Select “No” if the SF-425 still needs to be submitted.


Item 6:


Item 7: Enter the month, day, and year of the last day covered by the report (e.g., December 31, 20XX; March 31, 20XX; June 30, 20XX; or September 29, 20XX).


Item 8: Indicate the reporting term (e.g., 1st Semi-Annual or 2nd Semi-Annual). Select “other” if the report does not cover a 6-month period and provide information on the period covered by the report.


Item 9: Enter the title of the ANA project, the name of the individual who prepared the report, the date, their email address, and phone number. Note: the performance narrative referenced here starts on page 2.


Item 10: If attachments are being included with the report, list each of the attachments.


Item 11: Self-explanatory.


Item 12a: Enter the name and title of the authorized representative of the grantee. This individual will be the one certifying the accuracy of the report. Note: This cannot be the Principal Investigator/Project Director.


Item 12b: Enter the signature of the authorized representative certifying the report, no other project staff can sign the OPR.


Item 12c: Enter the telephone number, including the area code and extension number, of the authorized representative certifying the report.


Item 12d: Enter the email address of the authorized representative certifying the report.


Item 12e: Enter the month, day, and year the report is being submitted.


Item 13: Leave blank.


ONGOING PROJECT PROGRESS


  1. Objective Work Plan Status/Update


Item 1: Select “yes” if you need to make any changes to the Project Scope, Goal, Objectives, or Activities in the Objective Work Plan (OWP). Select “no” if no changes need to be made to the OWP. Select “no” if activity dates changed due to a Carry Over Budget (COB) or No-Cost Extension (NCE). Changes in activity dates do not change the nature of the project, they just reflect that you have experienced delays due to unexpected circumstances or challenges. Please do not request an OWP update due to changes in activity dates. 


Item 2: Provide an explanation of the changes you intend to make and if you have requested these changes from the ANA office.


Item 3: The approved OWP will pre-populate in this section when using GrantSolutions. This has been entered by your ANA staff; you should not enter anything here.



Status of Actives: Identify the status of each activity. This column should be updated accordingly. From the drop-down menu, select the correct status:


B. Staffing and Human Resources


Item 1: Select “yes” if you have any vacancies that are associated with this project. Select “no” if you do not have any vacancies that are associated with this project.


Item 2: If “yes” is selected, list the positions that are vacant or were vacant as of 30 days prior to the end of this reporting period. Also, indicate reasons for vacancies and actions taken or to be taken to fill vacant positions.


Item 3: Select “yes” if you had any changes or turnover in project staff, consultants, or contractors during this reporting period. Select “no,” if not.


Item 4: If “yes” is selected, list the affected positions, explain the reason for the change, state how long the position had been open, and if the position has been filled.


Item 5: Staffing table


Note: A job is classified as being currently filled and required for this project to be completed. Complete the table as follows:


C. Challenges

Challenges are any issues or events that have negatively impacted the implementation of your project. Challenges occur for nearly every project and can be overcome through careful planning and monitoring. In some cases, technical assistance can be provided to assist grantees in overcoming challenges. Note: Reporting on challenges does not reflect negatively on grantees, as all projects encounter difficulties. ANA encourages and appreciates detailed feedback on the challenges that grantees experience and how grantees approach such challenges.


Item 1: Select “yes” if your project encountered any challenges during the reporting period. Select “no” if you encountered no challenges.


Item 2: If you select “yes,” please provide a description of each challenge in the first column in the table below. In the second column, select “yes” if you have overcome the challenge or select “no” if you are still encountering this challenge. In the third column, describe how you overcame the challenge, if you selected “yes,” or identify your plan to address the challenge, if you selected “no.” Please be as detailed as possible, as the more information ANA receives on grantee challenges, the better we can assist grantees in the future.


Item 3: Select “yes” if the project could benefit from ANA-provided training or technical assistance at this time. Select “no”, if not.


Item 4: If you select “yes,” describe the services you would like to receive.



D. Financial


Item 1: Select “yes” if the grantee had trouble accessing (drawing down) funds from the Division of Payment Management during the reporting period. Select “no,” if not.


Item 2: If “Yes” is selected, explain the problem and if it was resolved.


Item 3: Select “yes” if you have made changes to your budget that required prior approval during this reporting period. Select “no,” if you have not. For more information on prior approval, see 45 CFR 74.25 and 45 CFR 92.30. In general, prior approval is needed for grant modifications that request any of the following: making any change in scope; making changes in any salary greater than 25 percent; re-budgeting more than 25 percent of the federal funds awarded, adding new line items; making sub-awards, transfers, or contracting of any work not approved in the original application; requesting additional federal funds; moving funds from direct costs to indirect costs and vice versa; and transferring funds allotted for training allowances to other budget categories.


Item 4: If “Yes” is selected, explain the request that was made and if it was resolved.


Note: This does not take the place of submitting a formal request. All standard procedures for requesting a budget modification must be followed.


Item 5: Financial table:

Enter the federal and non-federal forecasted cash needs from the Standard Form (SF) 424A of the approved grant application for the reporting period. Enter the actual cash needs (expenditures) for the reporting period, which should align with what is reported on the SF-425. This information is cumulative and should be maintained from the beginning of the grant to the last day of the budget period.


Item 5a: If the amounts forecasted in your SF-424A at the beginning of the budget period and actual amounts are not the same, explain the reason for the difference for each quarter. Reasons can be hiring delays, dates of high cost purchases that were made early/late, project delay in start date – whether project start-up or late award notification from ANA, etc.


Item 6: Select “yes” if you anticipate obligating all of the federal funds awarded for the project period by the project period’s end. Select “no,” if not.


Item 7: Select “yes” if you have any pending amendments with ANA. Select “no,” if not.


Item 8: Select “yes” if your project has generated any program income as a result of project activities. Select “no,” if not.


Item 9: If “Yes” is selected, indicate how much was generated and from what source.


Item 10: Identify how your program income will be utilized to support the project.


E. Other
Include any additional information your organization would like to share with ANA regarding your project.




F. Native Assets Building Initiative (NABI) Grants

These questions apply only to projects funded under the Native Asset Building Initiative and the Assets for Independence programs.